A gripping spade is used to dig a drainage trench in clay. Regional variations exist but the newcastle is pretty standard. Blade is narrow only 3-4 inches wide but 18 inch to 2ft long. Bulldog leaflet below shows range.
http://www.bulldogtools.co.uk/products/construction/spades/
Bulldog are not cheap but then they do last longer than a lifetime. One of my spades belonged to my grandfather and is still in daily use.
Personaly I always found a pick axe most useful for digging out clay, then use the spade to throw the clay out the hole.
http://www.pavingexpert.com/tools01.htm
EDIT: Just noticed your wrote "We're digging one at a time and shoring up." So may only be one man digging at a time after the first few feet if you are using spades?
Or just use this guy's method!
Surely a power tool, not mattock, to break the clay up, then shovel it out?
http://www.screwfix.com/p/spear-jackson-cable-laying-all-steel-shovel/23950#rating_link_anchor
from a review:-
"Using this spade to dig trenches in narrow places and to remove clay in thick slices.
It feels strong to use and does not give any signs of bending....it's from the "neverbend" range by Spear and Jackson although this is not obvious from the product write up.
Just get a mini digger and do it in less than half a day, dig in morning, fill in afternoon.
Where is the spoil going that comes out? Hand digging will leave a massive pile on the edge of the hole unless you are going to move it well away.
Just had a look at the weather and it's still low, going to be -5º over night in North London. Organising the rabble around the weather will be difficult.
Been busting my ass to make sure everything's in place to get going on 23rd only to be thwarted by the weather!
depends whether it falls into the hole.
My 3 tonne digger will easily dig 2.5 mtrs but it is advisable to use a bog mat at the edge of the hole otherwise you end up with the digger falling into the hole you have just dug as the side collapses.
How can you tell how deep they'll dig? This one for instance, couple of metres?
http://www.erento.co.uk/hire/construction-machines-building-site/plant/mini-digger/7147400627.html
Posted By: willie.macleodget your friends to barrow the concrete from the wagon to the hole if they want to help but make the digger do the digging work.
Good point. Our cheapest (by far) concrete quote comes from local concrete supplier just around corner but they don't have pumps.
You wont go down 2.5M with a micro digger . I think you will need at least a 1.5Tonne ( which would almost do that depth )but much better to go for a 3 tonne as they are much more comfortable than the 1.5 which bounces you around and wants to pull itself into the hole . All that said if you have the access much better than any hand tool .